Sunday, after I heard about Shmulik, I assumed that they would stop working on the house until after the shiva. By chance, I was home in the morning and drove by the building site. I was surprised to find Yossi (the plumber) there. And I was more surprised to see that he had an old copy of the plans in his hands.
He was working on the connection from the basement bathroom to the drainage pit (which I now know is a בור משיכה, in Hebrew ) . The problem was that the old plans that were in his hands show the bathroom in a different location from where it is on the current plan. When I saw what was happenning and then finally understood what was going on, I drove home and printed a copy of the basement plans from my computer. Yossi said it is not a problem to leave it there. I spoke to Josh and Alan, and both said it is not a problem to move it. So, if everyone is right, it is not a problem. I also think, it is not a problem, it will just have to be moved.